Villers Dépôt — Solges 000
EN
Enerfip Renewable energy Financé
Ce projet est clôturé. L'analyse ci-dessous reflète les informations disponibles au moment de la souscription et n'a pas été mise à jour.

Villers Dépôt — Solges 000

Average
64
score / 100
Yield
9.0%/yr
Duration
24 months
Min. ticket
50 €
Amount raised
1.3 M€
Invest →
À propos

Financing of guarantee deposit (1 065 k€) and PTF deposits (150 k€) required for application of Villers photovoltaic project (35.5 MWc) to CRE tender, via project company Solges 000. Project located at Villers-Saint-Sépulcre (Oise, 60), on industrial brownfield. Project at near-RTB stage: land acquired, building permit obtained and purged, connection secured, revenue in course of obtaining via CRE tender 9th period (July 2026).

Plateforme · 23.0/25
A1 · Statut réglementaire 8.0/8✓ max
  • agrément AMF licence AMF currently valid, fonds propres-2022-2 licence verified
  • Maximum score
A2 · Track Record 6.0/6✓ max
  • Default rate 0.00% → 6/6
  • Delay rate 0.32% (<5%) → 6/6
  • Average realised return 7.95% compliant with announced renewable energy range (5-9%) → 6/6
  • A2 = (6×0.5 + 6×0.3 + 6×0.2) = 6/6
A3 · Rigueur de sélection 3.0/4bon
  • Documented selection process (published risk score 2/5, internal committee), but overall selection rate not explicitly published
  • Leading renewable energy platform in France since 2014, 537 projects financed
A4 · Santé financière 3.0/4bon
  • Independent profitable platform (net income approximately 600K€ 2022), more than 10 years in existence, 30-50 employees, consistent growth
  • Acquisition of Lumo end of 2025
  • No listed institutional shareholder → 3 points vs 4 points for group subsidiary
A5 · Protection investisseurs 3.0/3✓ max
  • agrément AMF licence → reflection period 4 days plus mandatory continuity plan (1 point)
  • Segregated accounts required by agrément AMF status (1 point)
  • Enerdeal secondary market operational since 2023 (1 point)
Projet · 41.0/75
B1 · Instrument & Structure 8.0/10bon
B1.1: 5/5 - Simple bonds at fixed rate, French law
B1.2: 2/3 - société dédiée (SPV) Solges 000 dedicated, clear French law but issuer remains group entity
B1.3: 1/2 - Senior rank claimed, no known senior debt on société dédiée (SPV), not formally registered
B2 · Opérateur & Track record 7.0/15faible
B2.1: 2/4 - Armen Sedefian identified, team listed, limited public profile
B2.2: 2/5 - Founded 2021, <5 years, 0 MWc connected documented, 53 MWc RTB/advanced, development stage
B2.3: 1/3 - Previous fundraising Villers Foncier on Enerfip, no documented repayment
B2.4: 2/3 - No collective insolvency proceeding found, strained group balance sheet (revenue 2.4M€, outstanding 11M€, young structure)
B3 · Garanties & Sûretés 8.0/15
B3.1: 6/9 - Pledge of Solges 000 shares plus pledge of CDC receivable (1 065 k€)
B3.2: 2/4 - CDC debtor of pledged receivable is sound, but société dédiée (SPV) guarantor without documented high own equity
B3.3: 0/2 - No banking partner on this financing (<2M€, RF2 not triggered)
B4 · Structure financière 8.0/15
B4.1: 3/5 - PV project with target IRR 6.26%, CRE target tariff 85€/MWh over 20 years not yet obtained, development stage
B4.2: 2/4 - Guarantee deposit advanced in equity by promoter before crowd fundraising
B4.3: 2/4 - Stress case presented (70€/MWh vs 85€/MWh), taux de couverture de la dette >1.2x maintained
B4.4: 1/2 - taux de couverture de la dette displayed 1.23x-1.25x over duration, compliant with 1.2-1.5x threshold
B5 · Pré-commercialisation 4.0/10faible
  • ENERGY grid - Building permit obtained and purged (March 2024)
  • PTF received (April 2026), ENEDIS connection secured
  • CRE application to be filed July 2026, PPA/CRE contract not yet obtained
  • Near-RTB phase but missing revenue equals permit under instruction equivalent on income criterion: 4/10
B6 · Permis & Maturité 4.0/5bon
  • ENERGY - Building permit purged obtained March 2024, PTF received April 2026, connection secured
  • Construction authorisation obtained, appeal period expired
  • Network connection not yet finalised (deposits paid): 4/5
B7 · Marché & Localisation 2.0/3
  • French renewable energy market in growth (PPE3 adopted February 2026, CRE active)
  • Target tariff 85€/MWh in context of spot prices 40-44€/MWh - CRE CfD supplements
  • Risk of temporary nuclear/solar overproduction noted by RTE: 2/3
Points forts
✓Pledge of CDC receivable (1 065 k€) on sovereign public debtor.
✓Building permit purged, PTF received, ENEDIS connection secured: near-RTB project.
✓CRE tariff over 20 years if successful bidder: long-term revenue visibility.
✓Direct repayment by CDC if unsuccessful bidder: documented exit mechanism.
✓Enerfip PSFP licenced, 0% historical default rate, leading renewable energy platform in France.
Risques identifiés
!Revenue (CRE contract) not yet obtained: risk of non-selection at tender.
!Solges group founded in 2021, no documented connected MWc, modest balance sheet (revenue 2.4M€).
!Possible extension to 3 years: duration lengthening without additional guarantee.
!Risk of temporary overproduction in France (RTE) potentially affecting future CRE conditions.
!Land held by F01, not directly by Solges 000: complexity of ownership chain.
⚠ Avertissement sur les risques

Investir en crowdfunding comporte un risque de perte partielle ou totale du capital, ainsi qu'un risque d'illiquidité. Selon le baromètre France FinTech / Forvis Mazars 2025, 25 à 30 % des projets accusent un retard de plus de 6 mois et 4 à 6 % entraînent une perte définitive. Ne placez jamais plus de 5 à 10 % de votre patrimoine en crowdfunding et diversifiez sur au moins 10 projets. CrowdPickr est un service d'information indépendant, non agréé en tant que conseiller en investissement. Les analyses présentées ne constituent pas un conseil en investissement personnalisé.