← Retour aux projets
Charroux CRE — URBA 301
EN
Enerfip Renewable energy Financé
Ce projet est clôturé. L'analyse ci-dessous reflète les informations disponibles au moment de la souscription et n'a pas été mise à jour.

Charroux CRE — URBA 301

Strong
70
score / 100
Yield
6.75%/yr
Duration
48 months
Min. ticket
50 €
Amount raised
1.1 M€
Invest →
À propos

Construction of 14.3 MWc ground-mounted photovoltaic plant at Charroux (Allier, 03), held by URBA 301, subsidiary of Urbasolar (Axpo group). Project winner CRE in September 2025, at ready-to-build stage: land secured, building permit purged (Nov. 2022), connection accepted, CRE sales tariff 77.49 €/MWh over 30 years. Simple bullet bond over 4 years, without security.

Plateforme · 21.0/25
A1 · Statut réglementaire 8.0/8✓ max

Enerfip holds AMF licence agrément AMF fonds propres-2022-2 currently valid (verified against AMF register)

A2 · Track Record 6.0/6✓ max
  • Score adjusted based on live data: default rate 0.0%, delay rate 0.5%, target IRR consistent with announcements
  • Exceptional ENR history → 6/6
A3 · Rigueur de sélection 3.0/4bon
  • Selection process documented with internal committee and technical/financial analysis
  • Selection rate not published
A4 · Santé financière 3.0/4bon
  • Score adjusted based on live data: platform profitable (€773K profit 2024), >7 years existence, healthy growth €700M+ financed, no distress signal
  • Lumo acquisition 2025 strengthens position
A5 · Protection investisseurs 1.0/3faible
  • 4-day cooling-off period mandatory for agrément AMF (1 point minimum)
  • No secondary market mentioned
  • Segregated accounts not documented
Projet · 49.0/75 (54.0 brut, red flags −5)
B1 · Instrument & Structure 8.0/10bon
B1.1: 5/5 - Simple bonds fixed rate, French law
B1.2: 2/3 - Dedicated société dédiée (SPV) URBA 301, but junior rank explicitly stipulated
B1.3: 1/2 - Junior rank declared, senior bank debt expected, explicit subordination
B2 · Opérateur & Track record 13.0/15bon
B2.1: 4/4 - Directors appointed (Milloud, De Romanet, Attolini etc.), CVs attached
B2.2: 5/5 - Urbasolar >550 MWc operated, >750 plants commissioned, >20 years
B2.3: 2/3 - Urbasolar present Enerfip, outstanding 0€ reported, first closing URBA 301
B2.4: 2/3 - Negative equity URBA 301, but holding Axpo solvent
B3 · Garanties & Sûretés 3.0/15faible
B3.1: 0/9 - No security explicitly retained (N/A)
B3.2: 0/4 - Without formal guarantor
B3.3: 1/2 - Bank financing planned but not named
B4 · Structure financière 14.0/15bon
B4.1: 5/5 - CRE PPA 30 years at 77.49€/MWh, project IRR solid, contractualised revenues
B4.2: 4/4 - CAPEX 11.12M€, crowd 1.12M€ (~10%), equity capital plus bank debt cover 90%+
B4.3: 3/4 - Guaranteed tariff 30 years mitigates stress; business plan provided
B4.4: 2/2 - taux de couverture de la dette structurally >1.5 thanks to guaranteed CRE tariff 30 years
B5 · Pré-commercialisation 8.0/10bon
  • Building permit secured Nov
  • 2022 + connection accepted + CRE tariff 30 years signed Sept
  • Construction not yet started
B6 · Permis & Maturité 5.0/5✓ max
  • Building permit obtained and purged of all claims (Nov
  • Connection agreement received and advance paid
  • CRE tariff secured
  • Land secured
B7 · Marché & Localisation 3.0/3✓ max
  • French renewables market in strong growth, guaranteed CRE tariff independent of spot market, Allier sunshine adequate
  • Minor residual regulatory risk
⚠ Alertes détectées · −5 pts déduits
Aucune garantie réelle sur ce projet −5 pts

No security of any kind on 1.12M€ raising - no mortgage, pledge, or formal joint and several guarantee

Points forts
✓Urbasolar/Axpo: first-tier sponsor, >550 MWc operated, A+ rating
✓Guaranteed CRE tariff 77.49 €/MWh over 30 years - electricity price risk near zero
✓Building permit obtained and purged (Nov. 2022), connection accepted - permit risk eliminated
✓Enerfip: exceptional renewables track record, zero defaults in this segment
✓CAPEX 11.12M€ for 1.12M€ raised - crowd represents ~10% of total financing
Risques identifiés
!No security retained - bonds in junior rank without collateral protection
!Negative equity of URBA 301 (-19,679€ in 2025); SPV structurally loss-making before operation
!Bullet repayment at 4 years dependent on long-term bank refinancing or post-COD cash flows
!Construction delay or connection delay could postpone COD and repayment
!Concentration on single project (mono-asset SPV) without internal diversification
⚠ Avertissement sur les risques

Investir en crowdfunding comporte un risque de perte partielle ou totale du capital, ainsi qu'un risque d'illiquidité. Selon le baromètre France FinTech / Forvis Mazars 2025, 25 à 30 % des projets accusent un retard de plus de 6 mois et 4 à 6 % entraînent une perte définitive. Ne placez jamais plus de 5 à 10 % de votre patrimoine en crowdfunding et diversifiez sur au moins 10 projets. CrowdPickr est un service d'information indépendant, non agréé en tant que conseiller en investissement. Les analyses présentées ne constituent pas un conseil en investissement personnalisé.