Partial financing of the construction of a 4.45 MWp ground-mounted solar plant on a former quarry at Lesperon (Landes), developed by the Enoé group through the project company ENOVA PV 2. The permit is purged of any appeals, the CRE tariff has been secured over 20 years, and construction has been underway since February 2026, with commissioning scheduled for December 2026. These are simple bonds at 7 % over 4 years, repayable in fine, offered through local crowdfunding.
Permit purged of any appeals (May 2024), Enedis connection agreement in place, 35-year lease signed, construction started
Project of €4.1M (>€2M) with no banking partner documented in the file
Investir en crowdfunding comporte un risque de perte partielle ou totale du capital, ainsi qu'un risque d'illiquidité. Selon le baromètre France FinTech / Forvis Mazars 2025, 25 à 30 % des projets accusent un retard de plus de 6 mois et 4 à 6 % entraînent une perte définitive. Ne placez jamais plus de 5 à 10 % de votre patrimoine en crowdfunding et diversifiez sur au moins 10 projets. CrowdPickr est un service d'information indépendant, non agréé en tant que conseiller en investissement. Les analyses présentées ne constituent pas un conseil en investissement personnalisé.