Résidence Sainte-Marthe — Marseille 14
BR
Bricks Property development Financé
Ce projet est clôturé. L'analyse ci-dessous reflète les informations disponibles au moment de la souscription et n'a pas été mise à jour.

Résidence Sainte-Marthe — Marseille 14

Strong
68
score / 100
Yield
10%/yr
Duration
18 months
Min. ticket
10 €
Amount raised
3.5 M€
Invest →
À propos

New construction of 61 social dwellings (55 PLUS/PLS + 6 other) at 131 Chemin de Sainte-Marthe, 13014 Marseille, carried out by INOVA PROMOTION via the SCCV Marseille 131 Chemin de Ste Marthe. All dwellings sold in block under VEFA to Provence Métropole Logement (institutional lessor) at price €13.0M HT. Building permit obtained and cleared. Financing of land phase and initial works by bond loan of €3.54M at 10%/year over 18 months.

Plateforme · 19.0/25
A1 · Statut réglementaire 8.0/8✓ max
  • agrément AMF licence in valid force, fonds propres-2023-8 licence
  • Maximum applicable score
A2 · Track Record 5.0/6bon
  • Default 0% → 6/6
  • Delay 5.38% (threshold 5-15%) → 4.5/6
  • Net return 7.78% vs 10% announced, gap 2.22pp below lower bound → 1.5/6
  • Weighted score: (6×0.5)+(4.5×0.3)+(1.5×0.2)=4.65 → rounded 5
A3 · Rigueur de sélection 2.0/4
  • Selection process not detailed publicly, selection rate not published
  • Implicit mention of a process via agrément AMF licence
  • Score 2/4
A4 · Santé financière 2.0/4
  • Independent platform in strong growth (141M€, no.1 FR 2025)
  • Forced stoppage 7 months (Dec 2022-Jul 2023) and registre ORIAS deletion resolved
  • No identified institutional shareholder
  • Viability confirmed but regulatory history weighs
  • Score 2/4
A5 · Protection investisseurs 2.0/3
  • agrément AMF licenced → mandatory reflection period 4 days + Capsens continuity plan documented → 1 pt
  • Segregated accounts legally mandatory under agrément AMF → 1 pt
  • Secondary market not mentioned → 0 pt
Projet · 49.0/75 (54.0 brut, red flags −5)
B1 · Instrument & Structure 8.0/10bon
B1.1: 5/5 - Simple obligation fixed rate French law
B1.2: 2/3 - Dedicated SCCV but issuer INOVA ≠ SCCV project, indirect structure
B1.3: 1/2 - First rank mortgage promise not yet registered at file date
B2 · Opérateur & Track record 8.0/15
B2.1: 2/4 - Umut Inci appointed president, limited verifiable public information
B2.2: 3/5 - INOVA created 2011, capital €1M, but delivered operations not documented
B2.3: 1/3 - First Bricks operation, platform reputation not verified
B2.4: 2/3 - No insolvency proceeding identified, tight balance sheet (gearing non-calculable, equity €1M)
B3 · Garanties & Sûretés 10.0/15
B3.1: 7/9 - First rank irrevocable mortgage promise, authentic deed in process of registration
B3.2: 1/4 - Dedicated SCCV without history, equity not assessed, guarantor capitalisation not documented
B3.3: 1/2 - Financing from Banque des Territoires/CDC identified on lessor side, no direct promoter credit
B4 · Structure financière 12.0/15bon
B4.1: 2/5 - Loan-to-Cost (ratio prêt/coût total) 89.6% (crowd €3.54M/cost €3.95M), threshold >85% → RF7 triggered
B4.2: 2/4 - Contribution €412K i.e. 10.4% of total cost (threshold 10-15%)
B4.3: 3/4 - Block sale 100% secured to institutional lessor, commercial risk quasi-nil
B4.4: 1/2 - Gross margin €565K/€13M turnover ≈ 4.3%, below 8% threshold
B5 · Pré-commercialisation 8.0/10bon
  • 100% of 61 dwellings sold in block to Provence Métropole Logement under signed reservation contract (€13,001,138 HT)
  • Lessor licence obtained 23/01/2026
  • Firm commitment before works
  • No authentic VEFA deed yet regularised
B6 · Permis & Maturité 5.0/5✓ max
  • Building permit permis de construire 013055 24 00506 P0 issued 31/12/2024, cleared of all appeals
  • Amending permit issued 13/03/2026
  • Land not yet formalised (prerequisite for disbursement) but cleared building permit constitutes maximum progress
B7 · Marché & Localisation 3.0/3✓ max
  • Score adjusted thanks to live data: Marseille market rising, strong structural social housing demand
  • Block institutional sale at fixed contractual price eliminates market risk
  • Maximum score 3/3
⚠ Alertes détectées · −5 pts déduits
Ratio prêt/valeur trop élevé −5 pts

LTC calculated at 89.6% (threshold 85%) - bond debt to total cost ratio too high

Points forts
✓Block sale 100% secured to institutional lessor before works commencement
✓Building permit obtained and cleared, right to build definitively acquired
✓AIRCAP centraliser account with mandatory staged repayments on site
✓Banque des Territoires/CDC financing of €8.97M secured on purchaser side
✓First rank irrevocable mortgage pledge promise on 5 land parcels
Risques identifiés
!LTC 89.6% - bond financing covers quasi-totality of launch cost, own contribution limited to 10.4%
!Land not yet formalised at file date, VEFA not regularised - disbursement conditional
!No bank credit on promoter side, bond debt sole external financing source
!INOVA PROMOTION delivered operations history not documented in file
!Forecast gross margin 4.3% very low, little cushion in event of cost overrun
⚠ Avertissement sur les risques

Investir en crowdfunding comporte un risque de perte partielle ou totale du capital, ainsi qu'un risque d'illiquidité. Selon le baromètre France FinTech / Forvis Mazars 2025, 25 à 30 % des projets accusent un retard de plus de 6 mois et 4 à 6 % entraînent une perte définitive. Ne placez jamais plus de 5 à 10 % de votre patrimoine en crowdfunding et diversifiez sur au moins 10 projets. CrowdPickr est un service d'information indépendant, non agréé en tant que conseiller en investissement. Les analyses présentées ne constituent pas un conseil en investissement personnalisé.